Once products pass quality inspection at the factory, they are transported to site ready for construction. In the Philippines, installation is carried out by DELTA Group, which shares PEB Philippines' leadership and holds a PCAB Category B contractor's license through DELTA DNC Inc. Its skilled workers and supervising engineers make sure the building is erected exactly to the design and to a high aesthetic standard.
Members are joined with bolted connections and no welding on site, so a typical building goes up in about 4 to 6 weeks per 1,000 m² once the foundation is ready. See our equipment.
Installation process
- Prepare for erection. Check erection equipment and materials: quantity, safety and material quality.
- Erect the columns
- Erect the rafters
- Install purlins and bracing
- Align the frame of the first bay
- Erect the next bay
- Complete the remaining bays
- Install the ridge ventilator
- Final inspection before cladding
- Install cladding and finish